Road Improvement Schemes in South-east Wales

Part of 1. Questions to the Cabinet Secretary for Economy and Transport – in the Senedd at 2:02 pm on 22 November 2017.

Alert me about debates like this

Photo of Ken Skates Ken Skates Labour 2:02, 22 November 2017

Can I thank the Member for his question and invite him to ask any companies in the region that believe they are suffering as a consequence of these roadworks to make contact with my department without delay? We may be able to assist, and, if we can, we certainly will do. But the site topography, the very area that has caused the delay—the traffic management requirements for that area and the complex ground conditions have meant that the contractors have found that the project is far more difficult to deliver than they'd originally envisaged and, indeed, planned for. It was for that reason that I requested a comprehensive commercial project review, and the outcome of this review I am expecting imminently. As soon as I have received that review, I will be making a further statement.