Part of 1. Questions to the Minister for Economy, Transport and North Wales – in the Senedd at 2:13 pm on 9 December 2020.
Can I thank Mark Isherwood for his questions regarding this particular scheme? I should just point out as well, Dirprwy Lywydd, that, of course, increasing the availability of road space in north Wales on the A55 was a key feature of the UK Conservative Party manifesto, so it should be recognised that Mark Isherwood's own party is supportive of measures that would see increased volumes of traffic in north Wales on that key artery, the express way. What we're trying to do with the red route is to take existing traffic away from a key artery and put it onto another artery, so that we can then create a sustainable public transport and active travel solution for the most urban populated area of north Wales.
Mark Isherwood is right to say that COVID-19 has had an impact in terms of community engagement. It had been our intention to hold public information events during the spring of this year. But, of course, that couldn't take place as a result of the pandemic, but we're continuously reviewing our community and stakeholder engagement activity to ensure that all interested parties are updated regularly and, of course, safely, as our work on this scheme gathers pace.
In terms of some of the alternative suggestions that have been raised, we've looked into every alternative suggestion that has been raised with us—some quite enormous alternative schemes, others smaller schemes designed to address pinchpoints. But this route was determined to be the most suitable for the challenge that we face in that particular area of Wales.
And in regard to traffic and transport surveys, they are regularly conducted. Further transport and traffic surveys will be undertaken, particularly with regard to assessing how coronavirus might have affected transport and traffic volumes in the long term. But it should be noted, equally, that on the A55, volumes increased back to pre-COVID levels in August of this year, demonstrating that the A55 is very different to the M4 in that it has a far higher volume of traffic associated with the visitor economy and also haulage, and, of course, traffic associated, particularly in north-east Wales, with manufacturing industries as well, which aren't, unfortunately, as well catered for with remote working hubs as clerical work can be. So, it is a unique project for a unique problem.